Knife River - Belgrade began construction on the Gallatin Field Airport Improvement project on June 18th, 2007. It is anticipated to last through September and will consist of the following improvements to the Airport:

 1.)   Construction of 8,333 SY of Commercial Concrete Apron

2.)   Construction of 22,750 SY of Commercial Asphalt Apron and Holding Bay

3.)   Construction of 2,930 LF of Asphalt Service Road

4.)   Construction of 7,270 SY of General Aviation Taxiways

5.)   Storm Drainage Improvements

6.)   Runway and Taxiway Lighting Improvements  

These improvements that are being constructed are part of the 20 year Airport Master Plan which will eventually help facilitate an addition to the terminal and additional airplane traffic. More about the Airport Master Plan at Gallatin Field please click here and go to the Airports site.

DSCap3_0084.JPG

Project Highlights Include:

1.)   38,000 CY of Excavation

2.)   78,000 TN of Imported Pitrun

3.)   16,500 TN of Crushed Aggregate

4.)   9,000 TN of Asphalt Paving

5.)   4,000 CY of Concrete Paving

DSCap4_0083.JPG

DSCap2_0089.JPG

Click here to visit the City of Bozeman

If you have any questions or need assistance before or during the project, please contact any of the persons listed below:

 

Contractor:                                           Knife River            388-4035 ext 105

            Josh Walter                              Project Manager

            Mike Hoppel                            Project Superintendent

 

Engineer:                                              Morrison-Mairle       587-0721

                                                              Project Engineer

                                                              Project Engineer